Jay, any progress updates on the high riser version of the adapter?
Back in January, my existing foundry said I would have the high riser castings in March. In March, they said that the high riser castings would be delayed until May. I contacted them again at the beginning of this month, and they said July. Seeing a pattern?
So, I took back the high riser patterns from my existing foundry and brought them to a new foundry at the beginning of this month. They seem much more motivated to make this happen, and I'm hoping that they can resolve any quality issues quickly. They have promised me two prototype castings by June 15. If those look good (crossing my fingers), I should be able to get my production castings shortly thereafter.
As I have said here before, getting a good quality casting, on time, has been very difficult with the two foundries I've worked with so far. This latest foundry appears more professional, and I think they're hungry for work, so maybe they will deliver when they say...